| Task | Month | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | |
| 1. Update Needs Assessment | From month 1 to 5. Deliverable A , Demographic Projections delivered by Month 2 Deliverable B , Needs Assessment Report delivered by Month 4 | |||||||||||
| 2. Analyze Scenarios | From month 1 to 9. Deliverable C , Updated Baseline and No-Build Scenario delivered by Month 3 Deliverable D , Potential Scenario delivered by Month 6 Deliverable E , Recommended Plan Scenario delivered by Month 9 | |||||||||||
| 3. Review Vision, Goals, Objectives | From month 1 to 4. Deliverable F , Revised Goals and Objectives delivered by Month 4 | |||||||||||
| 4. Select Projects and Programs  | From month 2 to 8. Deliverable G , Universe of Projects delivered by Month 3 Deliverable H , Evaluate Projects delivered by Month 5 Deliverable I , Recommended Projects delivered by Month 8 | |||||||||||
| 5. Finalize Plan | From month 3 to 10. Deliverable J , Draft Plan for Public Review delivered by Month 9 Deliverable K , Adopt Final Plan delivered by Month 10 | |||||||||||
| 6. Adopt Amendments | From month 1 to 13. | |||||||||||
| 7. Other Ongoing LRTP Activities | From month 1 to 13. | |||||||||||
| Task | Person-Weeks | Direct Salary | Overhead (99.00%) | Total Cost | |||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| M-1 | P-5 | P-4 | P-3 | P-2 | P-1 | Temp | Total | ||||
| 1. Update Needs Assessment | 2.6 | 13.4 | 8.1 | 1.8 | 3.2 | 2.0 | 1.0 | 32.1 | $50,871 | $50,362 | $101,233 | 
| 2. Analyze Scenarios | 2.4 | 14.5 | 3.7 | 1.4 | 1.2 | 1.0 | 0.0 | 24.2 | $42,214 | $41,792 | $84,005 | 
| 3. Review Vision, Goals, Objectives | 0.4 | 2.1 | 0.3 | 0.1 | 0.2 | 0.0 | 0.0 | 3.1 | $5,641 | $5,584 | $11,225 | 
| 4. Select Projects and Programs  | 1.0 | 7.2 | 1.3 | 0.0 | 1.9 | 0.0 | 1.0 | 12.4 | $20,505 | $20,300 | $40,804 | 
| 5. Finalize Plan | 2.6 | 14.2 | 10.6 | 2.9 | 6.7 | 1.2 | 1.0 | 39.2 | $60,603 | $59,997 | $120,600 | 
| 6. Adopt Amendments | 0.1 | 0.4 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.5 | $970 | $961 | $1,931 | 
| 7. Other Ongoing LRTP Activities | 0.1 | 0.4 | 0.2 | 0.0 | 0.0 | 0.0 | 0.0 | 0.7 | $1,252 | $1,240 | $2,492 | 
| Total | 9.2 | 52.2 | 24.2 | 6.2 | 13.2 | 4.2 | 3.0 | 112.2 | $182,055 | $180,235 | $362,290 |