Project Identification

Unified Planning Work Program (UPWP) Classification

Boston Region MPO Planning Studies and Technical Analyses

Project Number 13299

Client  

Boston Region MPO

Project Supervisors

Principal: Mark Abbott
Manager: Seth Asante

Funding Source

MPO 3C Planning and §5303 Contract #108217

Schedule and Budget

Schedule: Twelve months after work commences

Budget: $90,000

Schedule and budget details are shown in Exhibits 1 and 2, respectively.

Relationship to MPO Goals

The Boston Region MPO elected to fund this study with its federally allocated metropolitan planning funds during federal fiscal year (FFY) 2020. The work completed through this study will address the following goal areas established in the MPO’s Long-Range Transportation Plan: safety, system preservation, capacity management and mobility, and economic vitality.

Background

As climate change progresses, the Boston region is likely to experience extreme weather effects, such as extreme heat and heat waves; intense nor’easters, tornadoes, and hurricanes; sea level rise and powerful tidal waves; and intense precipitation and flooding. These climate hazards will likely affect transportation systems:

In Massachusetts, there are several ongoing programs currently in place to address climate change resilience and adaptation. Several state agencies and municipalities are directly involved in these efforts. Massachusetts Executive Order #569 called for establishing an integrated climate change strategy for the Commonwealth.1 Because of the order, state agencies and authorities, as well as cities and towns are preparing for the impacts of climate change by assessing vulnerability and adopting strategies to increase the adaptive capacity and resiliency of transportation infrastructure and other assets. The Municipal Vulnerability Preparedness grant program (MVP) has supported and provided grants for cities and towns in Massachusetts to plan for climate change resiliency and implement priority projects.2 Many municipalities in the Boston region have participated in the MVP program, completed vulnerability assessments, and developed action-oriented resiliency plans—many of which include protecting vulnerable transportation infrastructure assets in their communities.

Also because of the executive order, the Massachusetts State Hazard Mitigation and Climate Adaptation Plan was developed.3 The plan provides a framework for linking mitigation measures with long-term climate adaptation, resiliency planning, and implementation. The plan provides information about activities at state agencies that are addressing risks and vulnerabilities from natural hazards and climate change and about how they are coordinating to ensure success. MassDOT and the MBTA are taking the following steps:

 

The MPO recognized the issue of climate change in its long-range transportation plan, Destination 2040, and emphasized the need to plan for resiliency in the transportation system to protect transportation investments. The MPO’s goal is to incorporate regular consideration of climate change vulnerability and risk and adaptation strategies in transportation decision-making at system and project levels. Many elements of the transportation infrastructure designed to function under historical climate conditions are vulnerable to future weather extremes and climate change, and making them resilient could lead to lower maintenance and other costs, fewer service disruptions, increased safety, system preservation, and economic vitality.

 

 

Objectives

  1. Increase MPO staff’s familiarity with resiliency planning for transportation system infrastructure
  2. Provide assistance to municipalities seeking to combat climate-related challenges
  3. Incorporate resilience into MPO-funded discrete and recurring studies

Work Description

The MPO staff will perform the following tasks in FFY 2020:

Task 1  Research Previous Work on Climate Change Impacts and Resilience

MPO staff will conduct an extensive literature review to research climate change impacts and adaptation options to protect vulnerable transportation infrastructure. Previous work completed by federal and state departments of transportation, educational and research institutions, MPOs, and municipalities will be synthetized to determine potential climate hazards, available data sources, vulnerable transportation assets, approaches used to identify vulnerabilities and adaptation options, and best practices. In addition, staff will ensure that the summary of the literature review provides information on state and municipal programs and plans and ongoing efforts so as to align this MPO work to support the goals and objectives of the Commonwealth.

Products of Task 1

Task 2  Research and Inventory Data Availability

Vulnerability assessments require a variety of data sources on transportation assets and climate change and extreme weather effects. MPO staff will identify data already available at Central Transportation Planning Staff and MassDOT and those that would be obtained from state and municipal entities. In addition, MPO staff will explore useful sources of information on climate data from other organizations that have experience developing or using climate projections, as these projections, models, and data sources are constantly evolving. Such data include projected climate data for extreme temperatures and precipitation, sea level rise, and coastal and riverine floods. MPO staff will also identify gaps in data sources to determine what necessary information is unavailable.

Product of Task 2

A summary of available data sources useful for vulnerability and adaptation assessments, climate change and extreme weather projections, and gaps in datasets

Task 3  Conduct Interviews and Survey

Tasks 1 and 2 will increase the MPO staff’s familiarity with climate change and resiliency and provide staff with knowledge and experience to develop a survey and interview municipalities in the Boston region.

 

The survey and interviews will enable the MPO staff to do the following:

Product of Task 3

A summary of the survey and interview process, including climate change-related problems in the Boston region communities, critical assets, policies and regulation issues, data sources, and analysis tools

Task 4  Select a Vulnerable Corridor and Incorporate Resilience Planning

MPO staff will select a corridor vulnerable to extreme weather effects, conduct a general vulnerability assessment, and identify adaptation options. The selected corridor will have multimodal transportation options and be critical to the transportation system in the Boston region. There must be sufficient data on the transportation assets and projected climate and extreme weather effects to conduct the assessments and develop adaptation options. This task will provide MPO staff with ideas of how to use available resources effectively to incorporate resilience into MPO-funded intersection and corridor studies and support the cities and towns in transportation resilience projects.

Products of Task 4

Task 5  Recommend Ways for Incorporating Resilience into MPO-funded Studies 

Based on the literature review, information gathered from the survey and interviews, data availability, and analyses, MPO staff will recommend approaches for incorporating resilience into MPO-funded discrete and recurring studies and provide technical assistance to communities. The recommendations would outline steps that the MPO could follow to support transportation resiliency projects in the Boston region.

Products of Task 5

Task 6 Document Findings

Staff will submit a report on the background of the study, research on previous work, agency and municipal input, data collection and sources, analyses of vulnerability and adaptation options, best practices, and recommendations to support municipalities seeking to combat climate-related challenges on transportation assets. The final document will be presented to the MPO board.

 

Products of Task 6

A final report documenting all of the project’s tasks and products, including recommendations and steps that the MPO could take to support transportation resiliency projects in the Boston region

 

1 Executive Order No. 569: Establishing an Integrated Climate Change Strategy for the Commonwealth, issued by Governor Charlie Baker on September 16, 2016.

2 The MVP Planning Grant offers funding to municipalities that wish to assess their vulnerability to climate change impacts, prepare for those impacts, build community resilience, and receive designation from the Executive Office of Energy and Environmental Affairs as a Climate Change MVP program municipality.

3 Massachusetts State Hazard Mitigation and Climate Adaptation Plan, September 2018

Exhibit 1
ESTIMATED SCHEDULE
Exploring Resilience in MPO-Funded Corridor and Intersection Studies


Task
Month
1 2 3 4 5 6 7 8 9 10 11 12
1.
Research Previous Work on Climate Change Impacts and Resilience
From Month 1, Week 1 to Month 2, Week 4.
2.
Research and Inventory Data Availability
From Month 2, Week 3 to Month 4, Week 2.
3.
Conduct Interviews and Survey
From Month 4, Week 1 to Month 6, Week 4.
4.
Select a Vulnerable Corridor and Incorporate Resilience Planning
From Month 6, Week 1 to Month 9, Week 4.
5.
Recommend Ways for Incorporating Resilience into MPO-funded Studies
From Month 7, Week 4 to Month 11, Week 2.
6.
Document Findings
From Month 1, Week 1 to Month 12, Week 4.
Deliverable
A
Delivered by Month 12, Week 4.
Products/Milestones
A: Final report

Exhibit 2
ESTIMATED COST
Exploring Resilience in MPO-Funded Corridor and Intersection Studies

Direct Salary and Overhead

$89,578

Task
Person-Weeks Direct
Salary
Overhead
(102.11%)
Total
Cost
M-1 P-5 P-4 Temp Total
1.
Research Previous Work on Climate Change Impacts and Resilience
0.5 1.5 0.0 2.0 4.0 $4,967 $5,072 $10,039
2.
Research and Inventory Data Availability
0.5 1.5 1.0 2.0 5.0 $6,413 $6,549 $12,962
3.
Conduct Interviews and Survey
0.5 2.0 0.0 2.0 4.5 $5,961 $6,086 $12,047
4.
Select a Vulnerable Corridor and Incorporate Resilience Planning
0.5 3.0 1.0 1.5 6.0 $9,129 $9,321 $18,450
5.
Recommend Ways for Incorporating Resilience into MPO-funded Studies
0.5 2.0 0.5 1.3 4.3 $6,313 $6,447 $12,760
6.
Document Findings
3.0 3.0 0.0 0.0 6.0 $11,538 $11,782 $23,320
Total
5.5 13.0 2.5 8.8 29.8 $44,322 $45,257 $89,578

Other Direct Costs

$422
Travel
$422

TOTAL COST

$90,000
Funding