Draft Memorandum for the Record

Boston Region Metropolitan Planning Organization (MPO) Transportation Improvement Program (TIP) Process, Engagement, and Readiness Committee Meeting Summary

 

 

February 13, 2025 Meeting

1:00 PM–2:49 PM, Zoom Video Conferencing Platform

Jen Rowe, Chair, representing Mayor Michelle Wu, City of Boston and the Boston Transportation Department

 

Decisions

The Transportation Improvement Program (TIP) Process, Engagement, and Readiness Committee agreed to the following:

 

 

Meeting Agenda

1. Introductions

J. Rowe welcomed committee members to the meeting of the TIP Process, Engagement, and Readiness Committee. See attendance below.

 

2. Public Comments

Marzie Galazka (Town of Swampscott) requested continued appropriation of funding for the Swampscott Rail Trail project, which is currently programmed on the TIP in federal fiscal year (FFY) 2028. She encouraged members to direct anyone with questions about the project to herself or to Dustin Kerksieck, a consultant for the project.

 

JR Frey (Town of Hingham) explained that the Town of Hingham had provided a comment on the draft Readiness Scenario requesting that the Hingham Improvements on Route 3A project (Project # 605168) continue to be funded in FFY 2026 instead of FFY 2027.


 

3. Action Item: Approval of December 19, 2024, TIP Process, Engagement, and Readiness Committee Meeting Summary—Ethan Lapointe, TIP Manager

Documents posted to the MPO meeting calendar

Vote

A motion to approve the minutes of the meeting of December 19, 2024, was made by the Metropolitan Area Planning Council (Eric Bourassa) and seconded by the Town of Arlington (John Alessi). The motion carried.

 

4. Action Item: Federal Fiscal Years (FFYs) 2026-30 TIP Readiness Status and Scenario—Ethan Lapointe, TIP Manager

Documents posted to the MPO meeting calendar

 

E. Lapointe introduced his presentation, explaining that the purpose was to discuss challenges and issues facing the MPO during the development of the FFYs 2026-30 TIP as well as to discuss potential solutions.

 

E. Lapointe noted that in the previous TIP Process, Engagement, and Readiness Committee meeting on December 19, 2024, he had discussed some of the changes to projects that were funded in FFY 2026 but recommended for delay into FFY 2027, contributing to the major deficit in FFY 2027. He also noted that MPO staff had expected low application volumes due to trends in recent years; however, there were ten applications for the Core Investment Programs (Complete Streets, Intersection Improvements, and Bicycle Network and Pedestrian Connections), 11 applications for the Transit Transformation Program, and seven applications for the Community Connections Program. Application levels are likely to remain high because some municipalities chose not to apply this year because of anticipated fiscal constraint.

 

E. Lapointe listed the projects for which applicants are seeking funding in FFYs 2026–30 and made some comments regarding design status:

 

E. Lapointe then shifted the conversation to the Readiness Scenario, noting that this information would also be presented at the MPO board meeting on February 20, 2024. First, he gave some background about how the data for each project was color-coded and displayed on the spreadsheets. He also noted that this new Readiness Scenario includes information about the number of years since each project has achieved a design milestone with the Massachusetts Department of Transportation (MassDOT). If a project has not achieved a design milestone in several years, this may be a sign that the project is at risk for delay. E. Lapointe brought up the TIP Project Cost Change Policy, which was published on September 23, 2021, and encouraged board members and members of the TIP Process, Engagement, and Readiness Committee to review the policy.

 

E. Lapointe gave an overview of TIP Readiness Days, which are a series of days in early February when MassDOT staff meets with each of the Massachusetts MPOs. The Readiness Days team solicits information from stakeholders to provide a recommended readiness year for each project. Project cost increases and budget deficits are usually not considered. This year, MPO staff have worked to better anticipate the news received on Readiness Days by hosting Quarterly Readiness Days and Subregional Readiness Days with project proponents and other stakeholders. This proactive solicitation of project updates is meant to reduce the number of surprises on Readiness Days.

 

E. Lapointe gave a forecast of the funding surpluses and deficits in the coming years. There are significant surpluses in FFYs 2025 and 2026, but there is a large deficit in FFY 2027. FFYs 2028 and 2029 have minor surpluses and deficits, and FFY 2030 has a surplus of about $40 million.

 

The surplus in FFY 2025 is a result of three projects being delayed from FFY 2025 to FFY 2026:

 

There are two projects that MPO staff have flagged as being at risk of being delayed from FFY 2025:

 

The surplus in FFY 2026 is a result of seven projects being delayed from FFY 2026 to FFY 2027. Four of these seven projects were also delayed from FFY 2025, and two of these four projects were delayed from FFY 2024 as well. E. Lapointe reminded the committee that four projects had been flagged as at risk for delay at the previous TIP Process, Engagement, and Readiness Committee meeting on December 19, 2024:

 

E. Lapointe then moved on to list the projects at risk for delay to FFY 2027 that were not included in the December 19, 2024 TIP Process, Engagement, and Readiness Committee discussion:

 

E. Lapointe described the projects that are at lower risk of being delayed from FFY 2026, but that are still important to monitor:

 

E. Lapointe then discussed projects programmed in FFY 2027. Only one project programmed in FFY 2027 is recommended to shift, while previous TIP cycles experienced much higher levels of delays in the second year of the TIP. The one project recommended for delay is:

 

E. Lapointe noted that there was a low volume of cost revisions for projects programmed in FFY 2027. However, this may be a result of projects being slow to reach new design milestones. MassDOT typically only updates project costs when design milestones are achieved. Therefore, a project that has not experienced any recent cost changes might not be a project with static cost; conversely, it may signal that the project is experiencing delays in its design and may see significant cost increases in its future.

 

E. Lapointe discussed delays of projects programmed in FFY 2028. MassDOT did not recommend any delays in this year, but the City of Boston recommended a delay for the Rutherford Avenue project (606226). The MPO staff are recommending a delay for Malden’s Spot Pond Brook Greenway project (613088) due to delays in the project’s design, lack of communication from the City about the project, and recent staff turnover. E. Lapointe also flagged a few projects that are at lower risk for delays:

There were no delays in FFY 2029, so E. Lapointe continued the discussion with a review of the major capital projects, beginning with MassDOT’s McGrath Boulevard Construction project in Somerville (607981). The 25 percent design update that was submitted on October 21, 2024, incorporated a revised cost estimate, prompting MassDOT to consider phasing the project. This project is at high risk for delay because of issues with Article 97 permitting surrounding a footbridge near the project area. The recent cost increase of this project will be funded with an increased obligation in FFY 2030. This project recently was awarded a Reconnecting Communities and Neighborhoods Grant for $43 million ($53.75 million total, when including the match), which must be obligated by FFY 2028. However, because of recent uncertainty over the use of federal funding, incorporation of this grant is not confirmed, and relying on this grant could pose risks in the future.

 

Next, E. Lapointe discussed Lynn’s Rehabilitation of Western Avenue project (609246). This project is at a high risk of delay and cost increase, as it has not received an updated cost estimate since 2018. Boston’s Reconstruction of Rutherford Avenue project (606226) is in a similar situation, as it has been more than four years since its last cost estimate was released. E. Lapointe then laid out the advance construction schedule for the Rutherford Avenue project, which is as follows:

 

These significant funding obligations may preclude the MPO from funding other projects programmed in the Long-Range Transportation Plan. E. Lapointe reminded the committee that Grant Anticipation Notes (GANs), the debt service for the Next-Generation Bridge Program, will reduce MPO Regional Target funding availability beginning in FFY 2032.

 

E. Lapointe laid out his key takeaways from this analysis. First, because the cost deficits in FFYs 2027 and 2028 outweigh the cost surpluses in FFYs 2029 and 2030, the deficits cannot be solved simply by delaying projects into the outer years of the TIP. Next, further cost increases area likely to emerge as proponents submit their 25 percent design updates in March. Finally, E. Lapointe recommended that the TIP Process, Engagement, and Readiness Committee consider the recommendations of the TIP Cost Change Committee. He gave the example of requiring project proponents to submit a revised cost estimate each year.

 

E. Lapointe discussed key considerations for this year’s TIP cycle. He stated that last year’s balanced strategy—of funding new projects and delaying current projects to address deficits while still addressing new priorities—may be more difficult to pursue this year due to the scale of the current deficit. Another compounding factor is that MPO staff received many project applications this winter, many of which were further along in the design process than projects currently programmed in the TIP. Lastly, funding has been relatively plentiful in recent years, despite budget deficits. If funding from the Bipartisan Infrastructure Law is lost and MassDOT resumes reserving funding for GANs, the budget issues will worsen.

 

E. Lapointe concluded the presentation by recommending that the committee consider a few topics for discussion, such as the near-term and long-term challenges for the TIP.

 

Discussion

E. Bourassa asked if projects programmed in FFY 2025 must be obligated by September 2025.

 

E. Lapointe answered affirmatively but noted that transit projects were distinct. Flexes to the Federal Transit Administration (FTA) need to be conducted by May 2025. He recommends that the amendment programming these projects be presented by the March 6, 2025, MPO meeting. However, these projects have much more flexibility as to when they must be advertised. They do not have to go out to bid by the end of the federal fiscal year like MassDOT projects must.

 

Lenard Diggins (Regional Transportation Advisory Council) asked if the recommendations from the TIP Cost Change Committee in 2021 were having any effect on current project delays. He also asked if there were any patterns that link projects that experience major cost increases and delays.

 

E. Lapointe answered that a significant number of the projects that are chronically delayed actually predate the TIP Cost Change Committee and have essentially been grandfathered in. In addition, the design requirements to reach 25 percent design have changed, so project proponents typically take longer to reach this milestone or require multiple resubmissions. E. Lapointe suggested that instead of having milestone-related requirements, such as necessitating a 25 percent design submission to receive funding for a certain year, there could be communication-based requirements instead. This could take the form of requiring annual updates of project cost and scope status.

 

J. Ostroff asked if the FTA has to approve TIP amendments.

 

E. Lapointe responded that MPO staff are working with the FTA to determine if this is a requirement, as well as if the FTA Flex amendment is feasible.

 

Brad Rawson (City of Somerville) asked if the MPO staff can determine which projects have significant scope changes that affect project timelines and costs. He suggested that the MPO board should discuss whether or not to fund projects that have changed drastically since they were scored and voted on.

 

Tom Bent (City of Somerville) agreed with B. Rawson and stated that this issue was one of the reasons why the TIP Cost Change Committee was formed.

 

E. Lapointe reminded the committee of his office hours that members can sign up for.

 

John Romano (MassDOT) proposed resurrecting the TIP Cost Change Committee.

 

L. Diggins suggested that the TIP Process, Engagement, and Readiness Committee can continue the work of the TIP Cost Change Committee.

 

E. Bourassa gave more context about the roles of the TIP Cost Change Committee. He explained that the committee considered reevaluating projects in an objective context to determine which would get delayed or removed from the TIP entirely. Many of the projects that continue to be delayed and increase in cost were programmed before the committee was formed. E. Bourassa proposed that the MPO board have a conversation about reconsidering the programming status of projects that cause persistent problems.

 

E. Lapointe stated that the MPO staff could invite project proponents to the March 13, 2025, TIP Process, Engagement, and Readiness Committee meeting to answer questions. He reminded the committee that MPO staff are re-scoring older projects that may have been evaluated using different criteria, on a different scale, or based on an out-of-date project scope.

 

J. Romano explained that the TIP Cost Change Committee required that project proponents submit information about scope changes when the project experiences a major cost increase. He expressed concern about keeping projects on the TIP when they have not had a recent cost update.

 

B. Rawson said that the large-scale projects should not be made into scapegoats simply due to their high costs. He also suggested having municipalities communicate about their project priorities if they have multiple programmed projects on the TIP.

 

 

5. Members’ Items

There were none.

 

 

6. Adjourn

A motion to adjourn was made by the Regional Transportation Advisory Council (Lenard Diggins) and seconded by the Metropolitan Area Planning Council (Eric Bourassa). The motion carried.


 

 

Attendance

Members

Representatives

and Alternates

City of Boston

Jen Rowe

Inner Core Committee (City of Somerville)

Brad Rawson

 

Tom Bent

Metropolitan Area Planning Council

Eric Bourassa

Massachusetts Department of Transportation (MassDOT)

Chris Klem

Massachusetts Department of Transportation

Tracie Lenhardt

MetroWest Regional Transit Authority (MWRTA)

Tyler Terrasi

MetroWest Regional Collaborative (City of Framingham)

Dennis Giombetti

Minuteman Advisory Group on Interlocal Coordination (Town of Acton)

-

Regional Transportation Advisory Council

Lenard Diggins

Town of Arlington

John Alessi

Town of Brookline

Erin Chute

 

 

 

 

Other Attendees

Affiliation

Aleida Leza

Anthony Jones

Barbara Lachance

Benjamin Coulombe

Dustin Kerksieck

Hanna Switlekowski

Jim Nee

Joan Meschino

John Romano

Jon Rockwell

Josh Ostroff

Joy Glynn

JR Frey

-

Federal Highway Administration

MassDOT

MWRTA

STV

MBTA Advisory Board

MWRTA

Third Plymouth District

MassDOT

The Engineering Corp. (TEC)

MBTA

MWRTA

Town of Hingham

Laurel Siegel

Lyris Liautaud

Marzie Galazka

Meghan McNamara

Melissa Santley

City of Medford

MassDOT

Town of Swampscott

Town of Lexington

MassDOT

Samira Saad

Sheila Page

Federal Highway Administration

Town of Wellesley

 

 

 

MPO Staff/Central Transportation Planning Staff

Tegin Teich, Executive Director

Adriana Jacobsen

Annette Demchur

Dave Hong

Lauren Magee

 

 


 


 

CIVIL RIGHTS NOTICE TO THE PUBLIC

Welcome. Bem Vinda. Bienvenido. Akeyi. 欢迎. 歡迎 .

 

 

You are invited to participate in our transportation planning process, free from discrimination. The Boston Region Metropolitan Planning Organization (MPO) is committed to nondiscrimination in all activities and complies with Title VI of the Civil Rights Act of 1964, which prohibits discrimination on the basis of race, color, or national origin (including limited English proficiency). Related federal and state nondiscrimination laws prohibit discrimination on the basis of age, sex, disability, and additional protected characteristics.

 

For additional information or to file a civil rights complaint, visit www.bostonmpo.org/mpo_non_discrimination.

 

To request accommodations at meetings (such as assistive listening devices, materials in accessible formats and languages other than English, and interpreters in American Sign Language and other languages) or if you need this information in another language, please contact:

 

Boston Region MPO Title VI Specialist

10 Park Plaza, Suite 2150

Boston, MA 02116

Phone: 857.702.3700

Email: civilrights@ctps.org

 

For people with hearing or speaking difficulties, connect through the state MassRelay service, www.mass.gov/massrelay. Please allow at least five business days for your request to be fulfilled.