Project | Proposed Change | Explanation | Section/Funding Source | Current Cost | New Cost | Difference |
FFY 2025 Statewide Highway Program | ||||||
608703: WILMINGTON- BRIDGE REPLACEMENT, W-38-029 (2KV), RT 129 LOWELL STREET OVER I-93 | Cost Increase | The project cost has increased following attainment of Plans, Specifications, and Estimates on May 30, 2025. The project is expected to advertise for bids on August 16, 2025. | NHPP, HIP-BR | $15,954,700 | $28,280,358 | $12,325,658 |
FFY 2025 Transit Program | ||||||
RTD0011195: METROWEST RTA - OPERATING ASSISTANCE NON FIXED ROUTE ADA PARATRANSIT SERVICE | Cost Decrease | The project cost has been adjusted to reflect the actual usage of FTA Section 5307 and State Contract Assistance funding for this effort in FFY 2025. The prior funding amount reflected projected expenditures. | FTA Section 5307, SCA | $2,000,000 | $1,004,541 | -$995,459 |
ADA = Americans with Disabilities Act. FFY = Federal Fiscal Year. FTA = Federal Transit Administration. HIP-BR = Highway Investment Program, Bridge. NHPP = National Highway Performance Program. RTA = Regional Transit Authority. SCA = State Contract Assistance. TIP = Transportation Improvement Program. |